Project Timeline
For more about these dates and deadlines, see the RGSFOP
dates and deadlines web page and the to
do list provided by them.
Dates for Flight Group 2 (August 10-19, 2006)
| Event |
Date Due |
| Flight
Physicals or Interval
Medical History Statements |
January 31, 2005 |
| Test
Equipment Data Packages (TEDPs) |
February 4, 2005 |
Personal
Identification Forms
(plus copy of 2 picture IDs)
|
April 14, 2005 |
| Make Travel Arrangements |
April 14, 2006 |
| Evacuation Plans and Badging Requests |
May 19, 2006 |
| Ship
GYRE robot to Houston |
August 4, 2006 |
Arrive in Houston |
August 9, 2006 |
| Safety and Program Orientation |
August 10, 2006 |
Physiological Training
Finalize construction |
August 11, 2006 |
| Test Readiness Review (TRR) |
August 14, 2006 |
| Flight Days (possible) |
August 15-18, 2006 |
| Ship
GYRE robot to Seattle |
August 19, 2006 |
| Return to Seattle |
August 20, 2006 |
| Final Report and Program/Hotel Evaluation |
sometime in 2006 |
|
|