Timeline
Project Schedule
| Milestone | Date |
|---|---|
| Feasibility Study presented to Hall Health Advisory Committee and SAFC | February 2008 |
| SAFC Request for Design Funding: $1,031,513 capital request of the SAFC | March 2008 |
| Design Phase Begins | November 2008 |
| Request for Construction Funding: $7,614,911 for direct cost and $1,000,000 for lost revenue due to reduced operations during project | June 2009 |
| Design Complete | December 2009 |
| Construction Begins | January 2010 |
| Full Occupancy | January 2011 |