HUB Renovation Project

HUB Project

In September the Board of Regents passed an allocation of Services and Activities Fee (SAF) funds to pay for the Pre and Schematic designs for a possible renovation of the HUB.

The current time line is as follows:

October – December 2008 Pre-Design
January – May 2009 Schematic Design
June 2009 Request for the SAF Committee to allocate funding for bonds to continue the project
July 2009 If SAF approves in June then Regents will be asked for the same approval
August 2009 If Regents approve then design and construction documents phase commences
January 2011 Construction commences
January 2013 Construction complete

In the meantime, Perkins+Will, in collaboration with Student Activities and Union Facilities, the HUB Project Committee, and the Capital Projects Office, is working on a new program and design for the HUB. As more information becomes available it will be posted on this site.