4/15/2015 ARCF Construction Updates:

The new Animal Research and Care Facility (ARCF) has reached several milestones this week, including first wells drilled for water control and initial drilling for site stabilization structures. Expansion of loading dock continues, placing the earth conveyor for the second phase of excavation, and modifying the Pacific street sidewalk to accommodate pedestrians during the construction. We are currently ahead of schedule and on-budget with this project and look forward to continued progress in the future.

Thank you to the design and construction teams for their outstanding support of this project, as well as the important contributions from so many members of the University community.