CRETM-LMER Columbia River-Fraser River ETM "Contrast Cruise"

Sunday, June 13 - Monday, June 14 Sproul (San Diego, CA) and Barnes (Seattle, WA) arrive Astoria, OR
Monday, June 14 - Tuesday, June 15 Onload both vessels, COE dock
Wednesday, June 16-Wednesday, June 30 Occupy Columbia River estuary
June 16 - 17
99U11: 1st 24-hr series at RM53 (Beaver Terminal) 
June 17 - 22
99L11: 5-day long series at lower North Channel (falling spring-into neap-increasing spring; few "imbedded" high-resolution series?)
June 22 - 23
99D11: 24-hr series at Clatsop Spit (duration and sampling frequency dependent on flow level?)
June 23 - 24
Dock break (less than 24hrs? Exact times to be determined)
June 24 - 28
99L12: 5-day long series at lower North Channel (neap-increasing spring; some "imbedded" high resolution series) 
June 29-30
99U21: 2nd 24-hr series at RM53 (Beaver Terminal)
Wednesday, June 30 Barnes offloads, COE dock
Thursday, July 1 - Saturday, July 3 Sproul and Barnes transit, Astoria, OR - Seattle, WA
Saturday, July 3 onload both vessels at UW
Sunday, July 4 Sproul and Barnes transit to Fraser River estuary
Monday, July 5 - Tuesday, July 20 Occupy Fraser River estuary
July 5 - 6
99FU11: 1st 24-hr upstream series near Port Mann Bridge
July 7 - 8
99FD11: 24-hr "estuary mouth" series at Sand Heads
July 8 - 18
99FL11: 10-day very long series near Woodward Island (increasing springs through middle of neaps; some "imbedded" high resolution series)
July 18 - 19
99FU21: 2nd 24-hr upstream series near Port Mann Bridge
Tuesday, July 20 Sproul transit to Seattle; Barnes works off mouth of Fraser/Friday Harbor on separate project
Tuesday July 20 - Wednesday, July 21 offload Sproul at UW
Thursday, July 22 - Monday, July 26 Sproul transit to San Diego, CA