Significant ARCF construction activities for this week include:

  • Excavation and hauling work continues– there will be increased truck traffic on NE Boat St, NE Pacific St, 15th Ave NE.
  • Underpinning soldier piles continues, footing demolition and work ongoing at the loading dock.
  • Install concrete curb cut to site entrance from Boat Street. One lane of Boat Street and sidewalk will be shut down.