Mobility Implications of School Crossing Guard Programs and School Walking Route Maps

PI: Kevin Chang (UI), kchang@uidaho.edu, ORCID: 0000-0002-7675-6598

Co PIs: none

AMOUNT & MATCH: $30,000 from PacTrans; $30,000 Match

PERFORMANCE PERIOD: 8/16/2017 – 8/15/2019

STATUS: Completed

CATEGORIES: Safe Routes to School, Route Maps, Crossing Guards

RESEARCH PROJECT HOT SHEET:

UTC PROJECT DOCUMENTATION:

FINAL PROJECT REPORT:

PROJECT DATA:

DESCRIPTION: This research aims to examine two specific components of walking and bicycling to school programs: 1) the formation, operation, and effectiveness of crossing guard programs and 2) the development, distribution, and usage of walking and bicycling to school walking route maps. The states of Washington and Idaho will serve as a baseline to determine if external factors such as legislative mandates drive certain policies and correspond to changes in behavior.

To complete this research study, a literature review will be initially conducted and will be followed by an analysis of existing data, interviews with school principals and administrators, site assessments, and the development of a final report.

DELIVERABLE DUE DATE DATE RECEIVED
Research Project Progress Report #1 4/10/2018 4/9/2018
Research Project Progress Report #2 10/10/2018 10/11/2018
Research Project Progress Report #3 4/10/2019 4/9/2019
No Cost Extension Request 6/15/2019
Draft Report 6/15/2019 8/8/2019
Final Project Report 8/15/2019 6/22/2020