Freeway Traffic Safety and Efficiency Enhancement through Adaptive Roadway Lighting and Control Enabled by Connected Sensor and Infrastructure Networks
PI: Yinhai Wang (UW), yinhai@uw.edu
Co PIs: Haizhong Wang (OSU), Zhibin Li (UW)
AMOUNT & MATCH: $180,000 from PacTrans; $180,000 Match
PERFORMANCE PERIOD: 12/15/2016 – 1/31/2018
STATUS: Completed
CATEGORIES: ITS, Connected Infrastructure, Mobility, Lighting
DESCRIPTION:
DELIVERABLE | DUE DATE | DATE RECEIVED |
Research Project Progress Report #1 | April 10, 2017 | April 15, 2017 |
Research Project Progress Report #2 | October 10, 2017 | October 9, 2017 |
No Cost Extension Request | November 30, 2017 | |
Draft Report | November 30,2017 | August 15, 2018 |
Final Project Report | January 31, 2018 | August 21, 2019 |